Pesco to suspend power supply to various areas due to maintenance work

0
190

PESHAWAR
The Peshawar Electric Supply Company (Pesco) would suspend power supply to various localities due to maintenance work. According to the company’s spokesperson, power Supply will remain suspended from 132 KV D.I.Khan Grid Station on February 23 from 9AM to 4PM, resultantly consumers of 132 KV D.I.LKhan grid connected 11 KV feeders will face inconvenience.
Power Supply will remain suspended from 132 KV Mardan Grid Station on February 23 and 24 from 10AM to 4PM, resultantly consumers of 11 KV MES and Mall Road feeders will face inconvenience. Power Supply will remain suspended from 132 KV Mardan Grid Station on February 23 and 24 from 9AM to 3PM, resultantly consumers of 11 KV Pakistan Chowk, Eid Ghah, Malakand Road, City 2, Dang Baba, Par Hoti, Shahbaz Ghari, New Baghdada, Shankar, Shah Dhandh, Col Jawad Shaheed feeders will face outages.
Power Supply will remain suspended from 132 KV Swat Grid Station on February 23,24,28 from 9AM to 2PM, resultantly consumers of 11 KV Malamjaba, Saidu Hospital, Bhadhai , Mengora 1,2, Kabal 1,2,3,4,5, Mengora 3,4, Barikot 2, Gulkadra, Marghuzar, Shingar Hospital, Gogdara, Takht Abad, Qambar, Saidu Baba, Hospital Express, feeders will face inconvenience.
Power Supply will remain suspended from 132 KV Mansehra Grid Station on February 23 from 10AM to 3PM, resultantly consumers of 11 KV Bafa, City 2, Shaheen Shaheed, Industrial Estate, Mangloor feeders will face inconvenience.
Power Supply will remain suspended from 132 KV Mansehra-Balakot Transmission Lineon on February 23 from 9AM to 4PM, resultantly consumers of 132 KV Balakot grid connected 11 KV Gharihabib ullah, Bohi , 132 KV Muzafarabad grid connected 11 KV State Bank, HPT, City 1,2,3,4,5,Water Supply, Noseri, CMH, Koharri, Barrawkot, Secretariat, Ghari Dopatta, Kohalla, Airport, Pattika , 132 KV Noseri grid connected 22 KV Athmaqam, Punjkot, Pattika, Nosadda feeders will face inconvenience.
Other areas that would face power suspension include 132 KV Tajazai grid connected 11 KV feeders on February 23 from 10AM to 6PM.